2 blocked drains

Reported via desktop in the Blocked Ditch category anonymously at 11:13, Tue 14 October 2025

Sent to Northumberland County Council less than a minute later. FixMyStreet ref: 8293379.

Reported over two years ago and nothing done. Blockages prevent water draining causing very icy road in winter. There is NO footpath and it is much used by both pedestrians and vehicles. Someone came to clear, lifted a clump of grass which he discarded at side of road and went away saying it needed the proper equipment, never to be seen again. Isn't two years more than your promised "time scale" to et things done? Also handrail still missing in Dispensary Street, also reported two years ago. Both these matters have also been put on Fix My Street by councillor Swinbank to no avail.

Updates

  • Thank you for contacting us about an issue with a drain.

    Our inspection teams will review your report within 10 working days.

    We will investigate drain reports that relate to the following:-

    • Where cars are having to drive on the opposite side of the road due to a blocked drain
    • Where pedestrians are having to walk off the pavement into the road due to a blocked drain
    • Where the road is not passable due to blocked drains
    • Where surface water from the highway is entering business premises
    • Where surface water from the highway is entering private property
    • Where there is a build-up of surface water at a bus stop
    • Where there is a build-up of surface water at pedestrian crossings

    Below are some examples of blocked drains:

    blocked drains

    Posted by Northumberland County Council at 11:13, Tue 14 October 2025

  • Great news, we have an update.

    Your report has been passed to the inspection team for assessment.

    We will provide an update once the inspection is complete.

    Posted by Northumberland County Council at 09:15, Fri 17 October 2025

  • Great news, we have progress on your report.

    Our inspection team have completed their investigations and instructed repairs to be completed. At this time the repair does not meet our immediate repair criteria.

    We have added this repair to our future schedule of works.

    State changed to: Action scheduled

    Posted by Northumberland County Council at 12:33, Wed 29 October 2025

  • Hand rail NOT. REPLACED. This is dangerous as required now evenings are dark, no lighting even from street lights. Drains have been cleared at last thank you.

    Posted anonymously at 11:44, Tue 11 November 2025
    Still open, via questionnaire

  • Still lacking handrail on top flight of steps at Windsor Gardens end of dispensary Street. Extremely dangerous at all times, but even more so in dark and bad weather. Drains have now been cleared thank you

    Posted anonymously at 17:45, Tue 9 December 2025
    Still open, via questionnaire

  • Hand rail still not replaced after two years’ wait, but drains done, with thanks

    Posted anonymously at 18:51, Tuesday 6 January 2026
    Still open, via questionnaire

  • Still no handrail, but then I have only been waiting 2 1/2 years!! still dangerous without it so maybe when someone falls it will get attended to

    State changed to: Fixed

    Posted anonymously at 21:20, Tuesday

This report is now closed to updates from the public. You can make a new report in the same location.